East Side Drive, Skippack Pike, North Wales Road, & Crestline Drive – DAY Postponed until 7/8-7/15

Whitpain Township

·         Walsh Construction will be installing right-of-way fencing on the northbound side Monday (6/27) through Friday (7/1) from 6 a.m. – 4:30 p.m.

 

Union Meeting Road – DAY

Whitpain Township

·         Walsh Construction will be placing embankment, excavating for detention basins, and installing right-of-way fencing northbound Monday (6/27) through Friday (7/1) from 6 a.m. – 4:30 p.m.

 

Jolly Road (T-346) – DAY Postponed until 7/6

Whitpain Township

·         Walsh Construction will be excavating and performing intermittent demolition on the Jolly Road mainline bridge Monday (6/27) through Friday (7/1) from 6 a.m. – 4:30 p.m.  Residents adjacent to the work area may experience increased noise levels due to the demolition work.